Canadian palladium producer Generation Mining finalises long-lead item orders for Marathon project


TSX-listed precious- and base metals miner Generation Mining has reported strong progress at its Marathon copper/palladium project, in Ontario, having finalised all long-lead item orders.

The company confirms procurement commitments now exceed C$500-million and are at or below the costs estimated in the project’s most recent feasibility study and construction budget.

Among the major long-lead items ordered is a larger semi-autogenous grinding (SAG) mill, which will provide Marathon with a processing capacity of 10.1-million tonnes a year and remove the need for a pebble crusher. The larger mill and its design also avoids C$12-million in future expansion costs.

“Our focus is on making decision today that improve how we build Marathon and how it performs for years to come. The larger SAG mill is a good example: it simplifies the plant, gives us full capacity from startup and avoids future expansion costs.

“Together with our progress on engineering and earthworks at site, decisions like this are focusing the project team on a clear project schedule,” comments Generation Mining projects VP Clinton Swemmer, referring to the company’s original plan to have 8.9-million tonnes a year of processing capacity in years one to three of operation using a smaller mill and expansion pathway.

Meanwhile, Generation says detailed engineering on the project by consultancy Ausenco is about 32% complete, while an early works programme will run through the fourth quarter and into 2027.

The Marathon project is expected to be a long-life, low-cost mining operation producing critical minerals essential to electrification, clean energy technologies and emissions reduction. It is expected to produce 2.1-million ounces of palladium, 532-million pounds of copper, 488 000 oz of platinum, 160 000 oz of gold and three-million ounces of silver over its 13-year mine life.



Source link

Related posts

Why Is Wheaton Precious Metals (TSX:WPM) Backing A New Copper Project?

D.William

Book Johannes Radebe: Finally Home Tickets

D.William

Support and Resistance Levels for 18 Instruments (Gold, Silver, Platinum, Palladium, Crude Oil, Natural Gas, Copper, and Ten Major Currency Pairs)

D.William

Leave a Comment